APPENDIX - CHAPTER 6.6 - CONSTRUCTION PROCESS
In order to better understand how a cost segregation study is conducted, it is helpful
to understand the construction process (i.e., how a building is constructed). The
following discussion provides a general overview of this process, from the conceptual
stage through the bidding, construction, payment, and completion stage of a project.
Although there may be certain facts and circumstances in specific geographic locales
that vary from what is presented here, the basic construction concepts are similar
in all locales. For purposes of this discussion, it is assumed that a fee contractor,
rather than an in-house labor force, performs the construction. For additional information
and a glossary of construction terms, refer to the MSSP Guide for Construction Industry,
which can be downloaded using the following link:
http://www.irs.gov/pub/irs-mssp/build.pdf
STAGES IN THE CONSTRUCTION PROCESS
The Construction Process is composed of six distinct stages, which are:
-
-
-
-
-
-
Each of these stages is discussed below in more detail.
1. Concept
All construction projects begin with planning and design, also referred to as "architectural
programming." Numerous overlapping steps occur during this conceptual or design
phase, prior to actual construction of the project.
An architect is the primary designer of a building or project and
controls the overall design, specifications, finished materials (e.g., brick, paint,
carpet, wall covering, etc.), and other architectural features of the building.
In addition, the architect supervises the engineers responsible for the structural,
mechanical, electrical, lighting and plumbing design of the building. Engineers
must always conform to the design requirements of the architect. Each member of
the design team must also be licensed with the proper state licensing authorities
where the facility is located.
back to the top
-
Planning & Architectural Programming
During the initial stages of the design process, the architect(s) and engineer(s)
have a number of client meetings in order to determine the purpose and objective
of the proposed construction. The primary activities, for which the project is being
constructed, as well as the relationships between spaces, are reviewed. Consideration
is also given to how well the completed project relates to adjacent buildings (if
any) and its surroundings. The preliminary programming produces a list of solutions,
alternatives, feasibility studies and costs estimates. After a review of the programming
statement, schematic plans are prepared.
-
Schematic Plans
Schematic plans are the first plans of a facility and show the interrelationship
between spaces and activities. All of the parties (architects, engineers, and the
client) review the schematic plans and make recommendations, as necessary. Any changes
are then incorporated into the final schematic plans. Revised schematic plans are
also known as "preliminary plans," and provide a graphic view of the project, the
refined details of how the project will look, and the relationship of all spaces.
Once the preliminary planning phase is complete, the project then enters a stage
involving the preparation of contract bid documents and working drawings.
2. Contracts and Bid Documents
In order to solicit construction bids, the builder must provide potential bidders
with working drawings and plans for the proposed structure, as well as project specifications,
the terms of which are spelled out in contracts.
-
Contract/Working Drawings/Plans
All projects, whether they involve new construction or expansion of an
existing structure, require the preparation of contract documents. The contract
working drawings and plans provide a pictorial representation of the construction
work, and specify or lay out the designer’s intentions for the facility. The drawings
illustrate, among other things, the appearance, layout, equipment, and amenities
of the project. These drawings show the architect’s plan/design for the building’s
overall appearance, such as finish materials, floor plans, sizes, and use of each
building area. Engineers design the building’s structural, mechanical, electrical,
plumbing and communication systems.
The architect also begins to gather project data to deal with problems or situations
that are expected to arise during the construction process, such as local zoning
requirements, local infrastructure, traffic, environmental and population impact,
acoustic, energy, lighting, and aesthetic considerations. Various consulting engineers
may also be utilized to solve specific project problems.
Numerous drawing plans are involved in a construction project, including the following.
-
Architectural Plans
The architectural plans indicate the layout of the project, such as floor plans,
elevations, and details of the construction and architectural finishes. These plans
are typically numbered sequentially with the prefix "A" for "architectural." "Plan
view," the most common type of an architectural plan, is an overhead view of the
spaces on a specific floor. These plans also indicate the length, width and various
heights of the structure and floor elevations. Plans may show notes of specific
construction information and may also contain details on a specific portion of work.
Exterior elevations show the exterior and the exterior finishes, and are similar
to photographs of the exterior. Architectural schedules on the plans indicate the
door types, windows, hardware, plumbing, and light fixtures in each room.
In preparing the plans, the architect utilizes graphic symbols, instead of words,
to indicate various facility conditions. These symbols indicate the various types
of material, sizes, and room finishes to be used. Symbols may be shown on the plans
themselves or in the legends of the plans. [A list of general symbols is shown in
the Appendix of Plan Reading and Material Takeoff, by Wayne J. DelPico, published
by R. S. Means Company.]
back to the top
A civil engineer is responsible for the proper drainage of a site, as well as the
design of land improvements, such as paving, curb and gutter design, retaining walls,
and drainage culverts. Site plans prepared by the civil engineer indicate the existing
and proposed grades of the land and the specific location of the facility on the
land.
-
Structural Plans
The structural plans are prepared by structural engineers and show the
structural design of a building. These plans incorporate foundation planning with
considerations for rain, snow, wind, earthquakes, and other natural phenomena. Structural
engineers design the facility for both "live" and "dead" loads of the building.
Live loads consist of the people, furniture, and other items that are not part of
the building, but are supported by the building. Dead load is simply the weight
of the building or structure itself.
-
Mechanical Plans
Mechanical plans are prepared by a mechanical engineer to show the design of the
various mechanical systems in the building. These systems must be designed to incorporate
the proper air conditioning, heating, and ventilation equipment, as well as adequate
plumbing, to meet the needs for all of the building’s designated activities.
Like the structural engineer, the mechanical engineer must design the mechanical
building systems to meet building "loads." For example, office work produces a certain
level of heat load, whereas cooking in a commercial kitchen may produce greater
heat loads. The energy use of the air conditioning, heating, pumps, and other building
equipment are monitored by the mechanical engineer and are considered when specifying
building equipment for an efficiently designed building system. Mechanical plans
are numbered with the prefixes "P" for "plumbing" and "H" for "heating, ventilating,
and air conditioning."
-
- Electrical Plans
Electrical plans are prepared by an electrical engineer, and show the electrical
distribution system for the efficient distribution of power in a building. The plan
design includes the distribution of electrical power from the utility company and
the distribution to power-specific equipment. Engineering design factors for the
overall electrical "load" of a building must also be considered (e.g., proper sizing
and arrangement of transformers, panel boards, circuits, wires, conduits and power
to the various machines, equipment and activities in the building). Electrical engineers
may also handle the lighting design requirements of the building, as well as specialty
areas such as a central security monitoring system, a computerized control system,
and fire and smoke management systems. Electrical plans are numbered with the prefix
"E" for "electrical."
back to the top
- Contract Specifications
The second part of the contracts and bid documents stage is the preparation
of project specifications, also known as "specs." Specs instruct the contractor
how to build the project, and consist of contract documents, the technical specifications
of the materials and the quality of the materials to be installed, and the workmanship
for installation of the materials. Given the amount of information that is required
to be included, specs have to be organized in a coherent manner. The most widely
accepted system for arranging construction specifications is called the CSI Master
Format. The CSI format, developed by the Construction Specification Institute, requires
four categories of information: bidding requirements, contract forms, contract conditions,
and technical specifications.
-
Bidding requirements
Bidding requirements describe the conditions of the bid to the owner, and encompass
the Invitation to Bid, the Instructions to Bidders, the Information Available to
Bidders, the Bid Forms and Attachments, and the Bid Security Forms. The type of
contract between an owner and a contractor dictates the form of the bidding conditions.
-
Contract Form
Contract forms are divided into sections, including the Agreement, the
Performance and Payment Bonds, and the Certificates.
-
Contract Conditions
The contract conditions include the General Conditions and Supplementary Conditions.
-
Technical Specifications
The technical specs are generally prepared for each specific project in the CSI
Master Format and these include hundreds, perhaps thousands of individual items
that will be installed in the project.
The CSI Format consists of 16 "Divisions of the Work", which are:
-
Division 1 - General Requirements
-
Division 2 - Site Work
-
Division 3 - Concrete
-
Division 4 - Masonry
-
Division 5 - Metals
-
Division 6 - Wood & Plastics
-
Division 7 - Thermal & Moisture
-
Division 8 - Doors & Windows
-
Division 9 - Finishes
-
Division 10 - Specialties
-
Division 11 - Equipment
-
Division 12 - Furnishings
-
Division 13 - Special Construction
-
Division 14 - Conveying Systems
-
Division 15 - Mechanical
-
Division 16 - Electrical
Each CSI Division is further sub-divided into three additional parts, called General,
Products, and Execution (Installation).
-
The General Section explains the scope or the limits of work for a particular CSI
Division and makes a correlation between the technical specifications and the general
and supplementary conditions of the contract. The administrative portion for any
trade (e.g., shop drawings) would be found in this section, as well.
-
The Product Section lists the materials to be used, by name and model number, and
explains the quality of materials and the basis for any substitution.
-
The Execution Section explains the method of material installation, techniques to
be used, and workmanship quality.
The American Institute of Architects (AIA) is a nationally recognized, professional
organization of architects. Over the years, the AIA has developed a document entitled
"AIA Document A201 - General Conditions of the Contract for Construction ("Document
A201"). The Document A201 is universally accepted in the construction industry and
provides the legal basis and description of the following contract items:
-
General Provisions
-
Owner
-
Contractor
-
Administration of the Contract
-
Subcontractors
-
Construction by the Owner or by separate Contractors
-
Changes in the Work
-
Time
-
Payments and Completion
-
Protection of Persons and Property
-
Insurance and Bonds
-
Uncovering and Correction of Work
-
Miscellaneous Provisions
-
Termination and Suspension of the Contract
Document A201 provides legal definitions of the elements in the construction process
and the items that will be provided by the contractor. Document A201 also details
how to prepare material submittals, shop drawings, and interim payment requests.
back to the top
3. Bidding
The third stage of the construction process is bidding. Once an owner determines
that a project is feasible and that construction financing is available, the owner
will solicit bids or proposals from general contractors and/or specialty contractors.
Owners generally use trade publications and newspapers in order to invite contractors
to bid on a construction job. A copy of "The Notice to Contractors" will be shown
in the project’s specifications, providing contractors with the bidding procedures.
The following is the sequence of events to prepare a contract bid:
-
The contractor obtains a copy of the plans and specifications from the owner in
order to prepare a formal estimate of the construction cost or bid (experienced
construction personnel prepare the bids).
-
The contractor reviews the contract plans and specifications to determine how to
build the project and to consider all the limitations or conditions the owner requires
for the project.
-
The contractor solicits bids from subcontractors, estimates their direct material
and labor costs, and evaluates the ultimate profit potential of the contract. The
amount of the bid covers the estimated costs and a profit for the construction project.
-
The owner evaluates all of the submitted bids and then awards the contract.
-
The contract document and specs contain the project start and completion dates,
the progress billing procedures, the insurance requirements, and other pertinent
information.
The preparation of a bid is the first step in the cost control system of a construction
project. The agreed-upon bid price then becomes the budget by which the actual expenditures
are measured and drawn against. The object of a cost control system is to provide
the general contractor and/or owner with information regarding actual project costs
versus the anticipated or budgeted costs. These cost comparisons become essential
for internal control purposes.
Standard cost manuals, such as the "R. S. Means Building Construction Cost Data,"
are used by a general contractor to compute a bid. These guides contain a compilation
of cost data for each phase of construction. There are also construction cost data
guides for both union and non-union wage rates. If the Service examiner needs to
estimate construction costs as part of the analysis of a study, it is important
to use the proper wage rates.
Subcontractors bid jobs in much the same way that a general contractor does. A subcontractor
may also solicit bids from sub-subcontractors for specialty construction.
Working drawings and specifications provide information to allow general contractors
to estimate the project’s construction costs. Along with using their own estimators,
a contractor usually has the subcontractor’s and the material supplier’s information
readily available. If necessary, a general contractor can perform the preliminary
details and/or shop drawings (see discussion on Appendix page 6.6-10) in order to
estimate the proper costs to construct various parts of a building. The general
contractor gathers all the information from his estimators and subcontractors and
then adds in an amount for overhead and profit. This final cost estimate is used
in the competitive bidding for the construction of a project.
The cost estimate of a building or project is broken down and organized by the construction
divisions shown in the specifications. The cost estimate is further detailed by
trade and by item. The general contractor may also have a bank of information in
order to estimate labor and material costs. Otherwise, the contractor will rely
on any of several cost estimating manuals [e.g., R. S. Means Building Construction
Cost Data (highly detailed), Marshall Valuation Services, etc.]
back to the top
4. Construction (Field Work)
The fourth stage of the construction process, called fieldwork, is the actual construction
of the project. Fieldwork is broken down into building permits, subcontractors,
scheduling subcontractors, shop drawings, project submissions, and change orders.
-
Building Permits
Before construction can begin, the appropriate municipality must issue
a building permit. Specifications and blueprints must be provided to the municipality's
building department, along with the application for a permit. The period of time
for a permit to be approved can be lengthy, especially in the case of new construction.
The general contractor or owner may also be required to submit results of soil testing,
environmental impact studies, and any other necessary testing or studies. Sometimes,
a public hearing is mandated, if there is opposition to the project. In most cases,
a permit is issued within a few months. The cost of the permit and any related studies
may be the responsibility of either the owner or the general contractor.
Construction projects must also follow the standards of the applicable building
code. A building inspector will be involved at various construction stages in order
to verify that the project is being constructed according to municipal code.
-
Subcontractors
Subcontractors range from a one-man operation to nationwide, publicly traded
corporations, or divisions of larger corporations. Subcontractors are distinguished
from general contractors by their limited scope of work, which usually involves
a special skill, knowledge, or ability. Subcontractors, which include plumbers,
electricians, framers, and concrete workers, generally enter into contracts with
the general contractor and may provide the raw materials used in their specialty
areas. The general contractor, not the owner of the property, pays the subcontractors.
Materials purchased by the subcontractors are generally delivered directly to the
job site. The subcontractors’ work may either be completed in stages, or it may
be continuous.
-
Scheduling of Subcontractors
The general contractor schedules the subcontractor's work so that the construction
runs smoothly and is completed on schedule. The general contractor is also responsible
for scheduling the subcontractor in such a way that one subcontractor does not hold
up another. This order on subcontractor sequencing is known as the "critical path."
An example of the sequence in scheduling subcontractors for a small project is as
follows:
-
Clear the land (which may include demolition of existing structures)
-
Excavate the land (which may include digging holes and leveling)
-
Pour the foundation
-
Frame steel and/or concrete
-
Rough framing
-
Rough electrical
-
Concrete flooring
-
Roofing
-
Heating and air conditioning
-
Ductwork for heating and air conditioning
-
Elevators and/or escalators
-
Sprinklers and other safety equipment
-
Install electrical fixtures
-
Insulate and weatherstrip
-
Frame windows and door sashes
-
Install tile and marble
-
Install suspended acoustical ceilings
-
Install toilets, sinks and other plumbing fixtures
-
Paint walls (inside and out)
-
Shop Drawings
Working drawings only include enough detail to show the general contractor
the overall layout of the building. The individual specialty trades and suppliers
use working drawings to produce shop drawings for items such as granite finishing,
cabinets and countertops, structural steel, etc. Shop drawings detail the specific
building components and are usually produced after the final design phase but before
the beginning of the construction phase. Drawings are prepared in accordance with
the instructions on Document A201. The architect/engineer will also check each shop
drawing for precise measurements and for compliance with the intended building design.
-
Project Submissions
Project submissions are an important part of the construction process. Each installed
building item must receive the architect’s approval to ensure that the item or product
is in conformance with technical specifications. Project submissions illustrate
each item's intended use, function, method of attachment or installation requirements,
and placed-in-service date. When the project is started, the architect and /or engineer
monitors the contractor’s progress and often approves the progress payments made
to the contractors. The architect/engineer may also make modifications to the building
plans as needed.
-
Change Orders
Change orders are the written contract revisions that increase or decrease the total
contract price. Change order documents contain the change order number, change order
date, a description of the change, and the amount of the change order. Contractors,
based on the terms of the contract, may also issue orders.
back to the top
5. Construction Payments
The fifth stage of the construction process is the construction payments stage.
All construction contracts extend over a period of time. The order of any business
operation is to collect money as soon as work is complete. When a contractor completes
a prescribed amount of work, the owner pays the contractor for the completed work.
-
Specifications for Payment
The specifications for contract payments are shown in Document A201, under the "General
Conditions for Construction Contracts." Document A201 contains AIA Forms G701 and
G702. Form G702 requires that the contractor break down the bid into various parts
of work. The project designer (architect or engineer) critically reviews the G702
schedule of values that are prepared by the contractor and either accepts or rejects
them. The close scrutiny of this form is due to the future release of funds that
will be used to pay for the progress (and ultimately the completion) of construction.
This form also provides the first basis for the construction cost control on a project.
The architect and/or engineer have a legal and fiduciary responsibility for the
accuracy of the cost allocations. The architect and the owner also want an adequate
and timely distribution of funds to ensure smooth progress payments and to ensure
that there will be the necessary funds to pay for the completion of the last portion
of the project.
It is also to the contractor’s benefit that items of construction be broken into
as many parts as possible. The more individual items of work that the contractor
can identify and complete, the more items of work he/she will be entitled to bill
and for which he/she will be timely paid. Typical schedules of values in the G 702
may be 15 to 20 pages long and may contain hundreds, if not thousands, of individual
cost items.
The contractor submits the G702 to request payment on a regular basis. The contractor
completes the G702 by listing the total construction cost for each item of work
completed to date. The amount previously paid for the work and the amount accomplished
in this billing period are subtracted from the total amount to arrive at the amount
of money remaining, minus a retainage for the completion of the work.
It is extremely important for the Service examiner to analyze the G702.
This document provides a breakdown and analysis of the construction costs and, since
it is prepared by 3rd parties, it provides an element of objectivity.
back to the top
6. Completion
The final phase of the construction process is known as the completion stage, and
it readies the building for occupancy.
-
As Built Plans
After a facility or project is completed, the architect and contractor prepare a
set of plans known as the "as built plans." These plans represent exactly how the
facility was constructed and they also incorporate all the changes to the original
construction plan. It is very important that the Service examiner utilize the "As-Built
Plans" when reviewing a cost segregation study because these represent the actual
construction of the project.
-
Notice of Partial Completion
In some instances, the owner may desire to occupy a portion of the completed
building. In that case, local building officials conduct an inspection to determine
if that portion of the facility meets all building codes and is safe to be occupied.
If approval is granted, a "Certificate/Notice of Partial Occupancy" is issued.
-
Notice of Substantial Completion
Local building officials issue this notice when 95 % of the construction is complete.
-
Notice of Completion/Certificate of Occupancy
A "Notice of Completion" is requested by the contractor/owner when the building
is 100% complete. The project must pass a final inspection by local building officials
in order for the "Notice of Completion" and the "Certificate of Occupancy" to be
issued. These documents are recorded at the office of the local recorder and the
property will be then appraised for property tax purposes.
SUMMARY AND CONCLUSIONS
This chapter provides an overview of the construction process and should assist
Service examiners in understanding terminology used in the construction industry.
In turn, this will assist in the review of cost segregation studies.